In linier project line of balance can be utilised to ensure efficiency between work activities.

When we say linier were not just talking horizontally but also vertically. Line of balance is best used to ensure that once a trade finishes their activities they have somewhere to go.

 

The attached picture demonstrates the use of line of balance on a tower block, each floor of the block is identified on the left with time going left to right. Each colour is a work activity. The efficiency is demonstrated by the lack of white space between work activities.

 

This can also be implemented on housing schemes as an example off horizontal linier movement.

 

To see how we can help you be more efficient get in touch

We provide planning solutions for builders, contractors, fit out contractors and larger sub contractors. We produce construction programmes, progress reporting and monitoring. Re-programming and all…

Follow us for more articles and posts direct from professionals on      
Property

Delay analysis isn't only for trying to claim an...

Delay analysis is key to understanding where you have lost time and why. Using it to identify your own shortcomings is…
EOT, Contract Negotiation

Issuing notices

Under your contract (without checking obviously) there is a requirement to serve notice to the client of delay along…
Planning, Holiday cover, Sickness cover

Were here to help

Mark Glen Consultancy are here to help with all your planning needs.From pre construction and tender planning to site…

More Articles

Planning, Risk Management, Delay mitigation

Critical or non critical?

Are you a critical or non-critical sub-contractor??? I know what you’re thinking and I agree all subcontractors and…
#planner, #planning, #holidaycover

Holiday cover & planning support

How are you managing your planners holiday cover?Is the plan to load their work onto the rest of your team and risk the…
Extension of time, Subcontract review

Condition Precedent, what does it mean and how does it...

A condition precedent is an event which must occur, before performance under a contract becomes due, i.e. before a…

Would you like to promote an article ?

Post articles and opinions on Leeds Professionals to attract new clients and referrals. Feature in newsletters.
Join for free today and upload your articles for new contacts to read and enquire further.